Ras Laffan

Latest works of Project Ras Laffan harbour expansion

The construction of the first phase of the big expansion of the LNG harbour in Ras Laffan, Qatar, is nearing its conclusion after nearly 3 years.

Abeko Dredging & Marine Contractors BV has the contract to supply machines and qualified personnel to Van Oord BVfor the construction of causeways and breakwaters with a total length of 22.5 kilometers. It is now putting the finishing touches to the construction before handover to the client. The contractors are currently busy with the last surveys and, if required, work together with the Abeko team to carry out any necessary adjustments and ensure that all constructions are in accordance with the specifications of the design, signed off in advance.